Project Timeline

2025

2025 Timeline

View completed 2025 project timeline

Completed
Current
2026

2026 Timeline

View 2026 project timeline

In Progress

Project Timeline 2026

Current Date: Week 4 of May 2026
Completed
In Progress
Planned / Future
Project TimelineQ1 2026Q2 2026Q3 2026Q4 2026
JanFebMarAprMayJunJulAugSepOctNovDec
12345123412341234512341234123451234123451234123412345
Partner Agreements and Coordination
Q1 Stakeholder Workshop (Remote)
Q2 Stakeholder Workshop (Remote)
Q3 Stakeholder Workshop (Remote)
Training of the Young Leaders (by UCAD)
Capacity Building Sessions for RAES and New RAs (by Dimagi)
Development of "How To Guides" (n=10)
Aim 3, Stage 2: Hybrid-Panel ITS Study Implementation
Participant Screening, Recruitment, and Onboarding
Baseline Surveying
Pre-Interruption Surveying (4 timepoints, every 2 weeks)
QA: Ongoing Review of Pre-Interruption Survey Data
Chatbot Onboarding
Chatbot Deployment (250 participants - Mass Deployment)
Post-Interruption Surveying (4 timepoints, every 2 weeks)
QA: Ongoing Review of Post-Interruption Survey Data
QA: Ongoing Chatbot Transcript Review
QA: Ongoing Chatbot Monitoring
QA: Ongoing Moderation of WhatsApp Groups
Design Iterations (Sprint 1)
Design Iterations (Sprint 2)
Design Iterations (Sprint 3)
Design Iterations (Sprint 4)
Design Iterations (Sprint 5)
End User Individual Interviews and FGDs
Stakeholder Interviews
Aim 3, Stage 2: Data Analysis
Ongoing Cost-For-User Analysis
Conduct Qualitative Data Analysis
Conduct Quantitative Data Analysis
Aim 3, Stage 3: Dissemination
Adaptation of FP Chatbot Evaluation Instruments
Refinement of LLM-Based Chatbot Cost Model
Development of Aim 3 Summary Report
Dissemination of Findings to Stakeholders (Remote Workshop/Meeting/TBD)
Drafting and Internal Review of Research Articles (n=2)
Submission of Manuscripts to Peer-Review Journals
Manuscript Revision and Resubmission

Task Status

TaskStatusTimeline
Q1 Stakeholder Workshop (Remote)CompletedMar - Mar
Q2 Stakeholder Workshop (Remote)PlannedJun - Jun
Q3 Stakeholder Workshop (Remote)PlannedSep - Sep
Training of the Young Leaders (by UCAD)In ProgressJan - JanCurrent
Capacity Building Sessions for RAES and New RAs (by Dimagi)CompletedFeb - Mar
Development of "How To Guides" (n=10)In ProgressFeb - DecCurrent
Participant Screening, Recruitment, and OnboardingIn ProgressJan - JanCurrent
Baseline SurveyingCompletedFeb - Feb
Pre-Interruption Surveying (4 timepoints, every 2 weeks)CompletedFeb - Mar
QA: Ongoing Review of Pre-Interruption Survey DataCompletedFeb - Mar
Chatbot OnboardingCompletedApr - Apr
Chatbot Deployment (250 participants - Mass Deployment)CompletedApr - Apr
Post-Interruption Surveying (4 timepoints, every 2 weeks)PlannedApr - Jun
QA: Ongoing Review of Post-Interruption Survey DataIn ProgressApr - JunCurrent
QA: Ongoing Chatbot Transcript ReviewIn ProgressApr - JunCurrent
QA: Ongoing Chatbot MonitoringIn ProgressApr - JunCurrent
QA: Ongoing Moderation of WhatsApp GroupsIn ProgressFeb - JunCurrent
Design Iterations (Sprint 1)CompletedApr - Apr
Design Iterations (Sprint 2)CompletedApr - May
Design Iterations (Sprint 3)CompletedMay - May
Design Iterations (Sprint 4)In ProgressMay - JunCurrent
Design Iterations (Sprint 5)PlannedJun - Jun
End User Individual Interviews and FGDsPlannedJun - Jun
Stakeholder InterviewsPlannedJun - Jun
Ongoing Cost-For-User AnalysisIn ProgressApr - JulCurrent
Conduct Qualitative Data AnalysisPlannedJun - Jul
Conduct Quantitative Data AnalysisPlannedJun - Jul
Adaptation of FP Chatbot Evaluation InstrumentsPlannedJul - Aug
Refinement of LLM-Based Chatbot Cost ModelPlannedJul - Aug
Development of Aim 3 Summary ReportPlannedJul - Aug
Dissemination of Findings to Stakeholders (Remote Workshop/Meeting/TBD)PlannedAug - Aug
Drafting and Internal Review of Research Articles (n=2)PlannedSep - Oct
Submission of Manuscripts to Peer-Review JournalsPlannedNov - Nov
Manuscript Revision and ResubmissionPlannedNov - Nov